Island Crest Park North Infield Turf Replacement

Project ID: 
(PA0117)
Project Type:
Parks
Project Status: 
Completed
Location: 
Island Crest Park
5500 Island Crest Way
Mercer Island, WA 98040

PROJECT LOCATIONProject Details/Neighborhood 

Island Crest Park - North Infield

​Background

The north field at Island Crest Park is the most used athletic field in teh City's park system, hosting recreational and league teams year-round. The synthetic infield turf is due for a lifecycle replacement and will be upgraded with cork and shock pad to replace teh current crumb rubber infill.  

Description

This project completes a lifecycle replacement for the north infield synthetic turf.

Project Timeline

Planning / Design: Q2-Q3 2023
Construction: Q4 2023-Q1 2024

Estimated Budget

2023: $400,000

Contact

Sarah Bluvas, CIP Project Manager: (206) 275-7864 or sarah.bluvas@mercerisland.gov

www.mercerisland.gov/PA0117

Design for North Infield turf replacement
Construction staging and access
Infield Turf Removal – The existing infield turf has been fully removed as of 02.01.24.
Bullpen Area – Removal of the turf and preparation in the bullpen area for new turf is almost complete.
City staff, the consultant from DA Hogan, and the FieldTurf crew walked the infield this week to inspect the gravel height.
FieldTurf started installing the new shock pad system for the bullpen the week of February 5.
A permanent pitcher’s mound replaces the portable mound previously used at the field.
The field will continue to feature three basepath lengths – 70’, 80’, and 90’.
New turf, cork infill, and shock pad systems have been delivered.
Island Crest Park Turf Install
ICP fans
ICP Gluing
ICP Infill
snow
snow removal
Completed field
GMAX testing
GMAX testing
Status Updates

May 2, 2024
When this project was completed back in March, technicians performed testing on the new infield turf to measure its impact attenuation, which is the ability of the playing surface to absorb shock from a collision. Staff recently received passing GMAX test results for the north infield turf. Industry standards specify that synthetic turf fields should stay at or below a GMAX measurement of 165. Our new turf system passed with a consistent range of 91-110 across all test points. This project will be closed out with FieldTurf and KCDA in the coming months.

March 22, 2024
Completed field     GMAX testing (2 photos)      GMAX testing
Photos:
1. Completed field
2. GMAX testing (2 photos)

This week, technicians performed testing on the new infield turf to measure its impact attenuation, which is the ability of the playing surface to absorb shock from a collision. During the tests, a 20-pound cylindrical weight is dropped three times from a height of 2 feet. The test is performed at 10 high-traffic locations depending on the sport; for baseball, these locations include the batter’s boxes, midfield, and first and third base running lines. Staff anticipate receiving the test report by the end of the month.

March 8, 2024

fans     gluing     infill     snow     snow removal

Photos:

  1. Fans
  2. Gluing
  3. Infill
  4. Snow
  5. Snow removal

After weather delays over the past two weeks paused work, the north infield turf replacement at Island Crest Park is finished. The City’s Parks Operations and Recreation teams cleared the field of snow and set up industrial fans on Tuesday to dry the field out for FieldTurf to finish gluing and applying infill on Wednesday and Thursday. Staff, the contractor, and the consultant completed the final walkthrough this morning, and the construction fencing has been removed. The field is now open for baseball practice, and the Varsity baseball team plays their first home game on the new turf on Monday, March 11.

February 16, 2024

ICP Turf install
Photo: Island Crest Park Turf Install
Crews made great progress this week installing new infield turf and the underlying shock padding. This project is on track for completion in March.

February 12, 2024

1.	City staff, the consultant from DA Hogan, and the FieldTurf crew walked the infield this week to inspect the gravel height.     2.	FieldTurf started installing the new shock pad system for the bullpen the week of February 5.      3.	A permanent pitcher’s mound replaces the portable mound previously used at the field.     4.	The field will continue to feature three basepath lengths – 70’, 80’, and 90’.     5.	New turf, cork infill, and shock pad systems have been delivered.

Photos:

  1. City staff, the consultant from DA Hogan, and the FieldTurf crew walked the infield this week to inspect the gravel height.
  2. FieldTurf started installing the new shock pad system for the bullpen the week of February 5.
  3. A permanent pitcher’s mound replaces the portable mound previously used at the field.
  4. The field will continue to feature three basepath lengths – 70’, 80’, and 90’.
  5. New turf, cork infill, and shock pad systems have been delivered.

Last week, City staff, the consultant from DA Hogan, and the FieldTurf crew walked the North Infield to inspect the base gravel height before turf install begins this week. Additionally, crews built the new permanent pitcher’s mound and installed new base anchors for the three basepath lengths – 70’, 80’, and 90’.

As part of this capital project, the City is shifting from the current rubber infill system to a cork infill + shock pad system. The shock pad sits between the gravel base layer and the artificial turf layer and provides an extra layer of impact absorption, lowering the risk of injury after a fall. Artificial turf also lasts longer when installed on top of the shock pad, as the pad protects the turf from abrasion caused by the gravel base layer. Using a shock pad requires less infill, so the new turf system should also be easier to maintain.

FieldTurf started installing the shock pad layer for the bullpen area last week, and the rest of the pad, as well as the turf and cork infill, have been delivered. The crews will start installing the rest of the shock pad system and laying turf this week, pending dry weather.

February 1, 2024

Infield Turf Removal – The existing infield turf has been fully removed as of 02.01.24.     Bullpen Area – Removal of the turf and preparation in the bullpen area for new turf is almost complete.
Photo 1: Infield Turf Removal – The existing infield turf has been fully removed as of 02.01.24.

Photo 2: Bullpen Area – Removal of the turf and preparation in the bullpen area for new turf is almost complete.

Progress continues on the North Infield turf replacement at Island Crest Park. The old infield turf has been fully removed, and the bullpen turf removal and site preparation is almost complete. Earlier this week, the construction crew hit an irrigation line when working in the bullpen area, but the pipe was repaired on Wednesday and no work time was lost. The identified parking area remains closed as construction continues.

January 22, 2024

Parking impacts for construction staging and access
Photo: Parking impacts for construction staging and access

Crews from FieldTurf plan to mobilize this week to begin removal of the old North Infield turf. Approximately 5-10 parking spaces may be closed off in the upper Island Crest Park parking lot to accommodate construction staging and access. Drive-through traffic will remain open during construction.

December 2023

Design for North Infield turf replacement
Image: Design for North Infield turf replacement
DA Hogan, the City’s consultant partner, completed the design for the North Infield turf replacement. This project includes a permanent pitcher’s mound and the option to turf the bullpen in between the North and South fields. The City plans to contract with FieldTurf through the King County Directors Association (KCDA) purchasing cooperative to install the new turf. Construction is on track to be completed before 2024 baseball season begins; the construction timeline will be added to the project page soon. 

September 2023

Design of the North Infield turf replacement is underway, and the consultant is also evaluating vendor opportunities through the King County Directors Association (KCDA) purchasing cooperative. Staff anticipate completing the turf replacement in winter 2023/2024.

March 2023

The City is contracting with DA Hogan to complete the design for this project.

Files: