2020 Overlay Road Construction Project - SE 78th St

Project ID: 
005
Project Type:
Street
Project Status: 
Completed

Overlay Road Construction at SE 78th Street (84th to 85th Ave) is scheduled for this summer. 

This is one of four road construction projects the City is undertaking this summer.

Please contact Clint Morris with questions 206-275-7807. 

Status Updates

August 31 Update: Paving is completed and ADA ramps are installed. Almost 100% complete.

August 20 Update: This week pavement grinding and patching was accomplished and asphalt  repaving is planned, bringing the project to 85% completion.

July 21 Update: Work will begin later this week with curb removals. New curbs and sidewalk ramps to be poured next week. 
 