2023 Residential Street Overlays

Project ID: 
23-16 (SP0100, SP0101, SW0137)
Project Type:
Street
Project Status: 
Completed
Location: 
Madrona Crest

23-16 Project Location​​Project Status

To help keep area residents informed of our construction progress, we will post project updates to this site on a regular basis. Click here to see status updates.

Project Details/Neighborhood 

  • Madrona Crest West (SE 36th Street, SE 37th Street, SE 39th Street & 86th Ave SE)
  • Madrona Crest East (SE 36th Street, SE 37th Street, SE 39th Street, 88th Ave SE & 90th Ave SE)

​Background

This annual program repairs and resurfaces arterial and residential streets through hot mix asphalt (HMA) overlays and chip sealing. The program includes upgrades to substandard residential streets, at the rate of about one location per biennium. Minor storm drainage repairs and minor water improvements will also be constructed. Utility work will be funded from the corresponding utility funds.

Description

This project covers the Madrona Crest West neighborhood (SE 36th, SE 37th, SE 39th Streets, and 86th Avenue) and the Madrona Crest East neighborhood (SE 36th, SE 37th, SE 39th Streets, 88th Avenue & 90th Avenue).  These roadways were significantly impacted by City water main construction in 2016 and 2022.  Work will include some overlays and some full pavement reconstruction based on roadway structural conditions.

Project Timeline

Budgeted ( Q2 of 2022)

Planning/Design (Q1 to Q2 of 2023)

Under Construction (Q2 to Q4 of 2023)

Completed (Q4 of 2023)

Estimated Budget

$1,200,000

Contact

Ian Powell, Street Engineer: 206-275-7813 or ian.powell@mercerisland.gov

www.mercerisland.gov/street23-16

 

 

 
SE 39th Paving
86th Ave Paving
Lakeside Industries milling asphalt to prep for paving at the intersection of SE 37th Street and 84th Ave SE.
Lakeside placing the top lift of new asphalt pavement along SE 39th Street between 84th Ave SE and 86th Ave SE.
Lakeside placing the top lift of new asphalt pavement along 86th Ave SE between SE 37th Street and SE 36th Street.
Repairing a damaged section of pavement on SE 36th Street before placing the final lift of asphalt.
Milling machine removing existing asphalt to prepare for paving on SE 39th Street
Paving the bottom layer of asphalt on SE 39th Street
Paving the final layer of asphalt on 88th Avenue SE
90th Removals
Bottom Lift 90th and 37th
Top Lift 36th and 88th
Installing asphalt berm on SE 36th Street.
Adjusting existing storm drainage structure to new asphalt grade.
Cleaning out a catch basin with a vacuum truck.
Status Updates

December 15, 2023
Installing asphalt berm on SE 36th Street.     Adjusting existing storm drainage structure to new asphalt grade.     Cleaning out a catch basin with a vacuum truck

Construction on this project is now 100% complete.  In November, crews from Lakeside Industries finished the last bit of punch list work, including final utility adjustments, drainage berms, and vacuuming out catch basins and sewer manholes to remove debris caused by construction activity.
 

October 25, 2023

Removing existing asphalt and grading the subgrade on 90th Avenue SE.     Paving bottom lift of asphalt on 90th Avenue SE and SE 37th Street.     Paving top lift of asphalt on SE 36th Street and 88th Avenue SE.

Photo 1: Removing existing asphalt and grading the subgrade on 90th Avenue SE.
Photo 2: Paving bottom lift of asphalt on 90th Avenue SE and SE 37th Street.
Photo 3: Paving top lift of asphalt on SE 36th Street and 88th Avenue SE.

Lakeside completed paving last month in the Madrona Crest East and Madrona Crest West neighborhoods. In October, Lakeside placed new gravel along the shoulders and adjusted the existing utilities to the grade of the new asphalt. Some minor adjustments are necessary to complete the project by the end of the year, depending on the weather. Please expect some intermittent travel delays as flaggers maintain a one-lane road during this work.

 

 September 8, 2023

Milling machine removing existing asphalt to prepare for paving on SE 39th Street     Paving the bottom layer of asphalt on SE 39th Street     Paving the final layer of asphalt on 88th Avenue SE

Photo 1: Milling machine removing existing asphalt to prepare for paving on SE 39th Street

Photo 2: Paving the bottom layer of asphalt on SE 39th Street

Photo 3: Paving the final layer of asphalt on 88th Avenue SE

The City’s paving contractor (Lakeside Industries) has completed approximately half of the paving in the plat of Madrona Crest East. The paving is complete on 88th Avenue SE, SE 37th Street and SE 39th Street. In the coming weeks these streets will have gravel added to the shoulders and the existing utility covers adjusted to the new asphalt grade.

The paving contractor is tentatively scheduled to be back the week of September 11th to start the pavement removal on 90th Avenue SE from SE 37th Street to SE 40th Street. Once removals are complete, Lakeside will pave 90th Avenue SE from SE 36th Street to SE 40th Street. They will also pave SE 36th Street from 88th Avenue SE to 90th Ave SE. After paving is complete these areas will also have gravel added to the shoulders and existing utility covers adjusted to the new asphalt grade. Please expect some travel delays in these areas as well as some heavy equipment and truck traffic. Flaggers will continue to maintain a one-lane road during 7:00 AM to 5:00 PM work hours. 

August 21, 2023
Lakeside Industries milling asphalt to prep for paving at the intersection of SE 37th Street and 84th Ave SE.     Lakeside placing the top lift of new asphalt pavement along SE 39th Street between 84th Ave SE and 86th Ave SE.     Lakeside placing the top lift of new asphalt pavement along 86th Ave SE between SE 37th Street and SE 36th Street.     Repairing a damaged section of pavement on SE 36th Street before placing the final lift of asphalt.
Photo 1: Lakeside Industries milling asphalt to prep for paving at the intersection of SE 37th Street and 84th Ave SE.
Photo 2: Lakeside placing the top lift of new asphalt pavement along SE 39th Street between 84th Ave SE and 86th Ave SE.
Photo 3: Lakeside placing the top lift of new asphalt pavement along 86th Ave SE between SE 37th Street and SE 36th Street.
Photo 4: Repairing a damaged section of pavement on SE 36th Street before placing the final lift of asphalt.

The City’s paving contractor (Lakeside Industries) will begin pavement removal and new paving in the plat of Madrona Crest East (SE 36th Street, SE 37th Street and SE 39th Street bounded by and including 88th Avenue SE and 90th Avenue SE) starting the week of  August 21st  for 2 to 3 weeks from 7 AM to 5 PM. Please expect some travel delays in these areas as well as some heavy equipment and truck traffic. Flaggers will continue to maintain one lane of traffic during 7:00 AM to 5:00 PM work hours. 

August 10, 2023 

86th Ave Paving

Photo: 86th Ave Paving
Lakeside Industries crews finished paving in Madrona Crest West this week and are moving to the Madrona Crest East area next week for roadway patching and other prep work. Paving of the East neighborhood is currently planned to begin the week of August 21st. This project is on track to have all road paving completed by the start of the school year. Shoulder rock, utility adjustments, and cleanup should be finished by the end of September.

 August 2, 2023
SE 39th Paving
Photo: SE 39th Street Paving

The City’s paving contractor (Lakeside Industries) will be completing asphalt repairs along Gallagher Hill Road from SE 36th Street to SE 40th Street. Please expect some travel delays in this area as well as some heavy equipment and truck traffic. Flaggers will maintain a one-lane road during work hours.

July 27, 2023

The City’s paving contractor (Lakeside Industries) will begin prep work in the plat of Madrona Crest West (SE 36th Street, SE 37th Street, and SE 39th Street bounded by and including 84th Avenue SE and 86th Avenue SE) starting in late July. Asphalt grinding and paving will follow the prep work. Following the paving in Madrona Crest West crews will move to the plat of Madrona Crest East (SE 36th Street, SE 37th Street, and SE 39th Street bounded by and including 88th Avenue SE and 90th Avenue SE). Please expect some travel delays in these areas as well as some heavy equipment and truck traffic. Flaggers will continue to maintain a one-lane road during 7:00 AM to 5:00 PM work hours. 

Planning/Design
The 50% design is complete. This year’s overlay project will pave the residential neighborhoods of Madrona Crest East and Madrona Crest West. This project is scheduled to bid later this spring with construction beginning in the summer.  The North Mercer Way segment of this project will be deferred from 2023 to 2024 construction to allow adequate time for the water system replacements on North Mercer Way to be completed this year.

 