Phase 1 PRV Replacement- Design

Project ID: 
WU0175
Project Type:
Water
Project Status: 
Completed

WU0175 Project Location​​Project Status

To help keep area residents informed of our construction progress, we will post project updates to this site on a regular basis. Click here to see status updates.

Project Details/Neighborhood 

  • PRV replacement locations are: 7549 SE 29th St, 2835 82nd Ave SE, 4110 78th Ave SE, 4753 Fernridge Ln

​Background

The City of Mercer Island (City) currently operates 85 pressure-reducing valve (PRV) stations to supply water to the Island. Previous investigations by the City showed that approximately 25 percent of the existing PRVs are in poor condition and many others have operational issues and deficiencies.

Description

An assessment of the 20 poorest condition PRV stations within the system was completed in 2021. It included a visual condition assessment and analysis to rank and prioritize them for replacement or upgrade in the coming years. Through the assessment, the five highest-risk stations were selected and four will be replaced under this project. These stations are located at four different locations.

Project Timeline

Planning/Design (Q4 2022 – Q3 2023)

Estimated Budget

$385K

Contact

George Fletcher, Senior Project Manager, 206-640-5379, George.fletcher@mercerisland.gov

www.mercerisland.gov/WU0175

 

 

 
What a 6” PRV looks like
Status Updates

July 2024 

What a 6” PRV looks like

Photo Caption: What a 6” PRV looks like

The construction contract for this project has been awarded to Fury Siteworks. Currently, the City is in the process of reviewing project submittals. Fury Siteworks is awaiting the delivery of project materials and anticipates beginning construction in early August. The first work site is located at 4108 78th Ave SE.

February 26, 2024

This program will replace numerous PRV stations within the City’s water system over the coming years. Phase 1’s design work is now completed and the project will be advertised for construction bids in the next couple of weeks. 

December 2023

The City of Mercer Island is awaiting Carollo’s 100% design submittal, scheduled for the end of December 2023.  Staff will review in January and hope to have the project out for construction bids in February 2024.

Planning/Design
The project is currently approaching the 90 percent design stage.