2020 Overlay Road Construction Project - SE 41st / SE 40th Streets (Residential)

Project ID: 
002
Project Type:
Street
Project Status: 
Completed

On July 15, 2020, road construction began on SE 41st / SE 40th Streets between 97th Ave and EMW. 

This is one of four road construction projects the City is undertaking this summer.

Please contact Clint Morris with questions 206-275-7807. 

Status Updates

Update as of August 31: Work began the week of July 13, the street was repaved July 20, and work is almost 100% complete.