To help keep area residents informed of our construction progress, we will post project updates to this site on a regular basis. Click here to see status updates.
Project Details/Neighborhood
9601 SE 36th St.
Background
The Facility Conditions Assessment of the Public Works building identified these retrofits required to continue to safely operate in the building.
Description
The project will include the following seismic improvements:
Complete removal of the existing green roof and its associated soils.
Roof replacement in the former green roof area and installation of roof drainage and stormwater conveyance, and replacement of other selectively removed roof areas.
Installation of anchoring between the walls and the wood diaphragms at the two higher level roofs (the second-floor office space and high bay garage).
Installation of a subsurface concrete grade beam along the exterior of each end of the high-bay garage doors of the mechanic shop.
Installation of bracing to numerous unbraced interior concrete masonry unit walls throughout the building.
Project Timeline
Construction occurring between March and July 2025.
Project Budget
The project budget of $1,138,420 is funded out of the Capital Improvement Project fund.
Construction continued above the PW Office this week. Perimeter reinforcement beams have been installed and have passed inspection. The contractor has installed new plywood sheathing in preparation for the new roofing membrane. The re-roof is expected to start next week and should take about 5 days to perform. Additionally, the green roof removal is scheduled to start next week and will continue through the following week.
Opens in new window
PDF Download
Word Download
Excel Download
PowerPoint Download
Document Download
Opens in new window
PDF Download
Word Download
Excel Download
PowerPoint Download
Document Download
Opens in new window
PDF Download
Word Download
Excel Download
PowerPoint Download
Document Download
Opens in new window
PDF Download
Word Download
Excel Download
PowerPoint Download
Document Download
Opens in new window
PDF Download
Word Download
Excel Download
PowerPoint Download
Document Download
March 6, 2025
Construction began this week with the general contractor, Casa Bella LLC, mobilizing to the site and installing a weatherproof shelter above the upper office roof. Initial work included removing the perimeter section of the roof and installing epoxy-threaded rods into the existing concrete masonry walls. Next week, crews will install reinforcement beams in the roof structure. Re-roofing should begin in about 2 weeks. The work area will remain accessible to employees as needed.